UPDATES - FYI

 

SW 10th Street Improvements


UPDATE - 18 March 2007

The traffic light at SW 10th St. and 28th Avenue is now operational

To the homeowners who use that intersection: please email the Board of Directors with your comments on how you view the effectiveness and timing of the new traffic light. For example, Is it improving safety? Is it increasing or decreasing the wait time to cross 10th street? Do you have any suggestions to improve its operation? The board has worked hard to make this happen, so please let us know if the result has been helpful to our neighborhood.

Al S.  


UPDATE - 06 March 2007

The following information was extracted from an email received by Dan Bogner from Jose Guerrero on March 8, 2007

"...Meeting Date: March 6, 2007 at 1:30pm

(Next Meeting is scheduled for April 3, 2007 at 1:30pm.)

Attendees:

Tim Butler

Ron Capobianco

Jose Guerrero

Jonathan Overton

The following is my summary of subject meeting:

:

:

Item 2: SR-869(SW 10th Street) @ SW 28th Ave.:

-Guardrail to protect mast arm on north side of the road has been installed. Contractor will place an asphalt pad(12"x12" x2") around posts when he is doing asphalt at Atlantic Blvd. @ Banks Road.

- A final inspection with Broward County Traffic Engineering Division has been scheduled for March 21, 2007. Ron Capobianco will provide Traffic Operations with a copy of the document showing county's approval & acceptance of the work done here to install a mast arm traffic signal.

:

:

Jose R. Guerrero, P.E.

Traffic Operations Projects Engineer

Florida Department of Transportation

Phone No. (954) 677-5274

Fax No. (954)777-4225

Toll Free:866-336-8435"

 


UPDATE - 04 February 2007

Update - several emails between Dan Bogner and Jose Guerrero from January 28 through February 1, 2007

From: <Timothy.Butler@dot.state.fl.us>

To: <jose.guerrero@dot.state.fl.us>

Cc: "Dan" <flwalleye@comcast.net>; <Hassan.Abedi@dot.state.fl.us>;

<jonathan.overton@dot.state.fl.us>; <jurrutia@petrohydro.com>;

<Ron.Capobianco@dot.state.fl.us>

Sent: Thursday, February 01, 2007 1:03 PM

Subject: Re: 10TH street light project

Good Afternoon Jose,

I meet with Juan from Petro Hydro and Lonnie from Sunshine Guardrail this morning.

We discussed the installation of the guardrail on SW 10 St. Lonnie said that he would try to schedule for Friday the 9th. I just spoke to Lonnie and he said that he schedule the installation of the guardrail for Friday February 9th.

Sincerely,

Tim Butler

Project Administrator,

954-958-7602

Fax 954-958-7660

timothy.butler@dot.state.fl.us

 

Jose R Guerrero/D4/FDOT

To "Dan" <flwalleye@comcast.net> 02/01/2007 07:25 AM

 cc Jonathan M Overton/D4/FDOT@FDOT, Ron Capobianco/D4/FDOT@FDOT, Hassan

Abedi/D4/FDOT@FDOT, Timothy Butler/D4/FDOT@FDOT, jurrutia@petrohydro.com

Subject Re: 10TH street light project

(Document link: Timothy Butler)

 

Dan,

This is what our folks from the Operations Center have told us. Signal> contractor(Traffic Control Devices, Inc.) can't install mastarm located on the north side of 10th Street, because their road contractor(Petro-Hydro, Inc.) hasn't been responsive enough in the installation of a guardrail that is needed to protect the mastarm's upright at that location. In our last meeting, held on January 16, 2007, our construction folks agreed to use their signal contractor(Traffic Control Devices, Inc.) for the installation of the guardrail in an effort to complete this project before March 23, 2007, when the signal construction contract will expire.

The remaining work consists of installation of the power by FP&L, installation of mastarm and signal heads on the north side, guardrail installation and final inspection by Broward County Traffic Engineering Division.

Since we aren't in control of the construction of this project and since I don't like to speak on behalf of construction, In the future please contact Ms. Maria Connolly, P.E., Ft. Lauderdale Operations Engineer at 954-958-7633. She oversees ALL projects in Broward County.

Thanks

Jose R. Guerrero, P.E.

Traffic Operations Projects Engineer

Florida Department of Transportation

Phone No. (954) 677-5274

Fax No. (954)777-4225

Toll Free:866-336-8435

 

"Dan" flwalleye@comcast.net

To jose.guerrero@dot.state.fl.us 02/01/2007 06:09 AM

cc

Subject Re: 10TH street light project

Jose:

Thanks for the reply, have not heard from Ron yet

 

----- Original Message -----

From: <jose.guerrero@dot.state.fl.us>

To: <Ron.Capobianco@dot.state.fl.us>

Cc: <jonathan.overton@dot.state.fl.us>; <Hassan.Abedi@dot.state.fl.us>; <flwalleye@comcast.net>

Sent: Monday, January 29, 2007 8:05 AM

Subject: Fw: 10TH street light project

Ron, please find attached an e-mail sent to me by one of our outside customer. Since this is a construction issue, would you please answer his concern?

Thanks

Jose R. Guerrero, P.E.

Traffic Operations Projects Engineer

Florida Department of Transportation

Phone No. (954) 677-5274

Fax No. (954)777-4225

Toll Free:866-336-8435

----- Forwarded by Jose R Guerrero/D4/FDOT on 01/29/2007 08:00 AM -----

 

"Dan" <flwalleye@comcast.net>

To <jose.guerrero@dot.state.fl.us> 01/28/2007 02:08 PM

cc

Subject 10TH street light project

Jose:

I believe we have passed the project date of completion for the traffic light project. What gives? The crew show up and maybe work for a hour or two and leave. When will this job be completed?

Dan

 


UPDATE - 19 December 2006

Update email received by Dan Bogner from Jose Guerrero on December 14, 2006

"...Sent: Thursday, December 14, 2006 2:51 PM

Subject: SR-869(SW 10th Street) @ SW 28th Avenue

This is an update on the status of subject intersection where we are installing a mast arm traffic signal. After meeting with our construction office on December 5, 2006, the revised anticipated completion date is January 30, 2007.

Signal contractor already poured all foundations, controller cabinet and upright at the S.E. corner. The service point is scheduled to be installed this month by FP&L

Any questions related to the above schedule should be directed to Ms. Maria Connolly, P.E., Ft. Lauderdale Operations Engineer at (954)958-7633.

Thanks

Jose R. Guerrero, P.E.
Traffic Operations Projects Engineer
Florida Department of Transportation
Phone No. (954) 677-5274
Fax No. (954)777-4225
Toll Free:866-336-8435..."

UPDATE - 31 October 2006

Update email received by Dan Bogner from Jose Guerrero on October 27, 2006

"...Sent: Friday, October 27, 2006 2:32 PM Subject: SR-869(SW 10th Street) @ SW28th Avenue

This is an update on the status of subject intersection where we intend to install a mast arm traffic signal. After meeting with our construction office on October 10, 2007, the anticipated completion date is still December 30, 2006, weather permitting.

Any questions related to the above schedule should be directed to Ms.Maria Connolly, P.E., Ft. Lauderdale Operations Engineer at (954)958-7633.

Thanks

Jose R. Guerrero, P.E.
Traffic Operations Projects Engineer
Florida Department of Transportation
Phone No. (954) 677-5274
Fax No. (954)777-4225
Toll Free:866-336-8435..."

 


UPDATE - 14 July 2006

The right turn lane at SW 10th Street & SW 28th Avenue has been completed!

 


UPDATE - 05 August 2006

Update email received by Dan Bogner from Jose Guerrero on August 2, 2006

"...Sent: Wednesday, August 02, 2006 8:14 AM
Subject: SR-869(SW 10th Street) @ SW 28th & 24th Avenues
 
This is an update on the status of projects at subject intersections.
 
As of July 28, 2006, work to construct an eastbound right turn lane onto SW 24th Ave. has been completed.
Installation of mast arm traffic signals at SW 28th Avenue is anticipated to be completed by December 30, 2006,weather permitting.
 
Any questions related to the above schedule should be directed to Ms. Maria Connolly, P.E., Ft. Lauderdale Operations Engineer at (954)958-7633.
 
Thanks
 
Jose R. Guerrero, P.E.
Traffic Operations Projects Engineer
Florida Department of Transportation
Phone No. (954) 677-5274
Fax No. (954)777-4225
Toll Free:866-336-8435..."
 

 

HISTORY

6 Lane Divided Roadway

On March 28, 2006 John Krane, a transportation planning engineer from the Department of Transportation responded to an inquiry from homeowner Dan Bogner regarding the status of improvements to SW 10th Street. Below is an excerpt from his email:

"...The Broward County Metropolitan Planning Organization (MPO) 2030 Long Range Transportation Plan (LRTP) has identified SW 10 Street from Powerline Road to I-95 as being improved to a 6-Lane divided roadway. As noted by Jonathan Overton, there is nothing in the current 5-Year Work Program of the FDOT. However, we update our Work Program annually, based on the annual MPO project priority list. Should this become a priority for the MPO, we would look to fund project development phases in our Work Program.

You should also be aware that in 2007 Florida's Turnpike is instituting open road tolling at the Toll Plaza, which will allow Sun Pass users to pass through the plaza without the need to pass through a toll booth.  There are not any current plans to widen the section between the Toll Plaza and Powerline Road. It is feasible, however, to expect this section of roadway to be studied in conjunction with any proposed widening east of Powerline Road, to ensure safe mobility along the entire segment to I-95...You may review the Plan in its entirety at the following URL:.."

http://www.browardlrtp.org/

 

New Traffic Signal & Right Turn Lane

On April 4, 2006 Dan Bogner received the following email from Jonathan M. Overton, the assistant district traffic operations engineer at the Florida Department of Transportation.

"...This is a follow-up email informing you of the construction schedule of 2 projects on SW 10th Street. 1. SW 28th Avenue - install new traffic signal Unless major emergencies occur (ie, hurricanes) that cause our resources to be diverted, construction is anticipated to begin by the end of December 2006. The current delay was caused by Hurricane Wilma. 2. SW 24th Avenue - install eastbound to southbound right turn lane Construction is anticipated to begin within 3 weeks. For project progress reports, please contact Ms. Maria Connolly, PE, Fort Lauderdale Operations Engineer copied on this email..."

On April 20, 2006 Dan Bogner was copied on the following email sent to Representative Slosberg

"...Mr. Representative Slosberg, This e-mail is to provide you with a status report of subject intersection where the Department intend to construct an eastbound right turn lane. Our Ft. Lauderdale Operations Center issued on April 17, 2006, a construction work order to their roadway contractor, Petro-Hydro, Inc. The expected completion date is June, 2006, barring any unforeseen circumstances..."